Consultation Launched for Hemerdon Tungsten Mine Permit

Public Consultation on Environmental Permit for Hemerdon Tungsten Mine

The Environment Agency is currently evaluating a request from Drakelands Restoration Limited, a subsidiary of Tungsten West plc, to amend its environmental permit for the Hemerdon Tungsten Mine. This process has been opened for public consultation, encouraging community members and interested parties to express their opinions on the proposed changes.

On 7 July 2026, the Environment Agency granted Drakelands Restoration Limited a Local Enforcement Position, permitting the temporary operation of a mobile crushing and screening plant at the mine site. Despite the initiation of operations with the mobile equipment, the Environment Agency stipulated that Drakelands must seek a permit variation to continue its use beyond the temporary allowance.

Details of the Permit Variation

Drakelands operates under an installations permit issued by the Environment Agency, which governs the site’s management, operation, and the monitoring of emissions. The proposed permit variation aims to permanently integrate the new mobile plant into the existing permit for the Hemerdon Mineral Processing Facility. Additionally, the proposal includes the extension of the permit boundary to encompass the mobile plant.

The Environment Agency is actively soliciting feedback from the local community and relevant stakeholder groups regarding the draft permit. Jay Rowntree, the area environment manager, emphasised the importance of this consultation, stating, “We allowed Drakelands to operate the mobile plant temporarily but made clear that a permit variation would be required for any longer-term operation.” He assured that the agency would meticulously review the application in accordance with all applicable environmental regulations and guidelines before making a final decision.

READ:  Koi Herpesvirus (KHV) Disease Outbreaks in 2026: What You Need to Know

Consultation Period and Submission of Comments

The consultation is currently open and will remain so until 11 December 2026. The Environment Agency is legally required to refuse a permit application only if it fails to meet certain legal standards set forth in environmental legislation, including the potential for significant environmental impact or harm to human health. Conversely, if the application aligns with all requirements, the agency is obliged to grant the permit.

For those who prefer a physical copy of the permit variation application, it can be obtained by reaching out to the Customer Contact Centre. Please note that there may be a fee to cover copying costs.

How to Participate in the Consultation

Participants may use the following methods to share their views:

  • Post: Environment Agency Permitting and Support Centre, Land Team, Quadrant 2, 99 Parkway Avenue, Sheffield, S9 4WF.

All comments must be submitted by 11:59 pm on 11 December 2026 to ensure they are considered in the decision-making process.