Significant Advancements at SIXEP Continuity Plant Highlighted by Recent Crane Lifts
Significant Progress at the SIXEP Continuity Plant
The SIXEP Continuity Plant (SCP) has reached a significant milestone with the successful completion of a series of major crane lifts at the Sellafield site. This new facility, being developed under the Programme and Project Partners (PPP) initiative, is now three-quarters complete and remains on schedule to commence operations by 2029.
The main structures of the plant have been finalised and are now protected from the elements. Current efforts are concentrated on the internal fitting out of the plant and the installation of specialised equipment essential for its operation.
Transitioning to a Modernised Operation
Upon its completion, the SCP will assume the responsibilities of the existing Site Ion Exchange Effluent Plant (SIXEP), which ha...